Percentage of total outdoor lighting fi xtures with solar lighting system, as per GRIHA (a minimum of
25% of total number or 15% of total connected load, whichever is higher) (1 point)
Responsibility: Electrical Consultant
Criterion 7 Plan utilities effi ciently and optimize on-site circulation effi ciency
Commitment
Minimize road and pedestrian walkway length by appropriate planning and provide aggregate
corridors for utility lines.
Optional clause
Demonstrated use of minimization and consolidation of transportation/service corridors and
shading of pedestrian roads, as per GRIHA (1 point).
Responsibility: Architect
Use of aggregate utility corridors, as per GRIHA (1 point).
Responsibility: Architect
Consolidation of utility corridors along the previously disturbed areas or along new roads in order
to minimize unnecessary cutting and trenching and ensure easy maintenance, as per GRIHA
(1 point).
Responsibility: Architect
Health and well-being
Objective
To protect the health of construction workers and prevent pollution.
Criterion 8 Provide minimum level of sanitation/safety facilities for construction workers
Commitment
Ensure cleanliness of workplace with regard to the disposal of waste and effl uent, provide clean
drinking water and latrines and urinals as per applicable standard. (2 points)
Mandatory clause
Compliance with National Building Code norms on construction safety for ensuring safety during
construction (1 point), as per GRIHA
Responsibility: Project Manager
Provision for health and sanitation facilities as specifi ed above (1 point), as per GRIHA
Responsibility: Project Manager
Criterion 9 Reduce air pollution during construction
Commitment
Ensure proper screening, covering stockpiles, covering brick and loads of dusty materials, wheel-
washing facility, and water spraying facility.
Percentage of total outdoor lighting fi xtures with solar lighting system, as per GRIHA (a minimum of
25% of total number or 15% of total connected load, whichever is higher) (1 point)
Responsibility: Electrical Consultant
Criterion 7 Plan utilities effi ciently and optimize on-site circulation effi ciency
Commitment
Minimize road and pedestrian walkway length by appropriate planning and provide aggregate
corridors for utility lines.
Optional clause
Demonstrated use of minimization and consolidation of transportation/service corridors and
shading of pedestrian roads, as per GRIHA (1 point).
Responsibility: Architect
Use of aggregate utility corridors, as per GRIHA (1 point).
Responsibility: Architect
Consolidation of utility corridors along the previously disturbed areas or along new roads in order
to minimize unnecessary cutting and trenching and ensure easy maintenance, as per GRIHA
(1 point).
Responsibility: Architect
Health and well-being
Objective
To protect the health of construction workers and prevent pollution.
Criterion 8 Provide minimum level of sanitation/safety facilities for construction workers
Commitment
Ensure cleanliness of workplace with regard to the disposal of waste and effl uent, provide clean
drinking water and latrines and urinals as per applicable standard. (2 points)
Mandatory clause
Compliance with National Building Code norms on construction safety for ensuring safety during
construction (1 point), as per GRIHA
Responsibility: Project Manager
Provision for health and sanitation facilities as specifi ed above (1 point), as per GRIHA
Responsibility: Project Manager
Criterion 9 Reduce air pollution during construction
Commitment
Ensure proper screening, covering stockpiles, covering brick and loads of dusty materials, wheel-
washing facility, and water spraying facility.