Page 51 - GRIHA Manual Volume I - Introduction to National Rating System
P. 51
38 GRIHA Manual: Volume 1
Optional clause
Annual water reuse of 25%, as per clause 21.2.5 (1 point).
Responsibility: Water Consultant and Plumbing Consultant
Annual water reuse of 50%, as per clause 21.2.5 (additional 1 point).
Responsibility: Water Consultant and Plumbing Consultant
Annual water reuse of 75%, as per clause 21.2.5 (additional 1 point).
Responsibility: Water Consultant and Plumbing Consultant
Recharge of surplus rainwater into aquifer, as per Table 21.2 of GRIHA (2 points).
Responsibility: Water Consultant and Plumbing Consultant
Waste management
Objective
To minimize waste generation; streamline waste segregation, storage, and disposal; and promote
resource recovery from waste.
Criterion 22 Reduction in waste during construction
Commitment
Ensure maximum resource recovery and safe disposal of wastes generated during construction and
reduce the burden on landfi ll (1 point).
Optional clause
Segregation of inert and hazardous wastes, as per GRIHA
Responsibility: Architect and Project Manager
and
Recycling and safe disposal of segregated wastes, as per GRIHA (1 point).
Responsibility: Architect and Project Manager
Criterion 23 Effi cient waste segregation
Commitment
Use diff erent coloured bins for collecting diff erent categories of waste from the building (1 point).
Optional clause
Provision of multi-coloured bins for waste segregation at source (1 point).
Responsibility: Architect and Project Manager
Criterion 24 Storage and disposal of wastes
Commitment
Allocate separate space for the collected waste before transferring it to the recycling/disposal stations
(1 point).
Non applicability condition proposed: This criteria shall not apply to projects that have organic
solid waste generation on site less than 100 kg/day
Optional clause
Annual water reuse of 25%, as per clause 21.2.5 (1 point).
Responsibility: Water Consultant and Plumbing Consultant
Annual water reuse of 50%, as per clause 21.2.5 (additional 1 point).
Responsibility: Water Consultant and Plumbing Consultant
Annual water reuse of 75%, as per clause 21.2.5 (additional 1 point).
Responsibility: Water Consultant and Plumbing Consultant
Recharge of surplus rainwater into aquifer, as per Table 21.2 of GRIHA (2 points).
Responsibility: Water Consultant and Plumbing Consultant
Waste management
Objective
To minimize waste generation; streamline waste segregation, storage, and disposal; and promote
resource recovery from waste.
Criterion 22 Reduction in waste during construction
Commitment
Ensure maximum resource recovery and safe disposal of wastes generated during construction and
reduce the burden on landfi ll (1 point).
Optional clause
Segregation of inert and hazardous wastes, as per GRIHA
Responsibility: Architect and Project Manager
and
Recycling and safe disposal of segregated wastes, as per GRIHA (1 point).
Responsibility: Architect and Project Manager
Criterion 23 Effi cient waste segregation
Commitment
Use diff erent coloured bins for collecting diff erent categories of waste from the building (1 point).
Optional clause
Provision of multi-coloured bins for waste segregation at source (1 point).
Responsibility: Architect and Project Manager
Criterion 24 Storage and disposal of wastes
Commitment
Allocate separate space for the collected waste before transferring it to the recycling/disposal stations
(1 point).
Non applicability condition proposed: This criteria shall not apply to projects that have organic
solid waste generation on site less than 100 kg/day