Criterion 22 Reduction in waste during construction
Objective
To ensure maximum resource recovery and safe disposal of wastes generated during construction,
and to reduce the burden on the landfi ll.
22.1 Commitment
22.1.1 Employ measures to segregate the waste on-site into inert, chemical or hazardous wastes.
22.1.2 Reuse/Recycle the segregated waste and unused chemical/ hazardous wastes such as oil,
paint and batteries.
22.1.3 Inert waste to be disposed off by municipal corporation/local bodies at landfi ll sites.
22.2 Compliance
The following documents are to be submitted.
22.2.1 Narrative indicating the quantum of waste generated during the construction activity,
and the storage facility for segregated inert and hazardous waste before recycling
and disposal
22.2.2 Layout (showing the location) and photo of the storage facility for segregated inert and
hazardous waste. The capacity of the storage facility has to be provided.
22.3 Appraisal (maximum 1 points)
22.3.1 Segregation of inert and hazardous wastes, as per clause 22.2. and
22.3.2 Recycling and safe disposal of segregated wastes, as per clause 22.2 (1 point).
Figure 8 Construction waste disposal
Criterion 22 Reduction in waste during construction
Objective
To ensure maximum resource recovery and safe disposal of wastes generated during construction,
and to reduce the burden on the landfi ll.
22.1 Commitment
22.1.1 Employ measures to segregate the waste on-site into inert, chemical or hazardous wastes.
22.1.2 Reuse/Recycle the segregated waste and unused chemical/ hazardous wastes such as oil,
paint and batteries.
22.1.3 Inert waste to be disposed off by municipal corporation/local bodies at landfi ll sites.
22.2 Compliance
The following documents are to be submitted.
22.2.1 Narrative indicating the quantum of waste generated during the construction activity,
and the storage facility for segregated inert and hazardous waste before recycling
and disposal
22.2.2 Layout (showing the location) and photo of the storage facility for segregated inert and
hazardous waste. The capacity of the storage facility has to be provided.
22.3 Appraisal (maximum 1 points)
22.3.1 Segregation of inert and hazardous wastes, as per clause 22.2. and
22.3.2 Recycling and safe disposal of segregated wastes, as per clause 22.2 (1 point).