Page 87 - GRIHA Manual Volume II - Introduction to National Rating System
P. 87
Sustainable site planning 79
So, depending on the type of lamps that will be included in calculation, the outdoor lighting load
to be powered by solar energy will vary. Therefore, if calculation is done as per option 1, then solar-
powered lighting load will be 4.58 kW. If calculation is done as per option 2, then solar-powered
lighting load will be 9.05 kW.
Note In case installation of a solar photovoltaic system has been planned on site to meet the requirements of GRIHA Criterion 18, the
electricity generated from this PV plant can also be used to power exterior lights. However, the solar energy requirements of Criterion 6
are independent of the requirements of Criterion 18.
Guide to use GRIHA online evaluation tool
Depending on the points that are being attempted in a project, click on the relevant boxes in the
‘Goals’ section. Given below is a snapshot of the GRIHA Criterion 6 template for a project where
all 3 points are being attempted. As soon as the user clicks on the box, the related compliance
documents get ticked automatically bringing to the notice of the user to provide all the required
documentation. Required supporting drawings and word documents can be uploaded using the
template.
So, depending on the type of lamps that will be included in calculation, the outdoor lighting load
to be powered by solar energy will vary. Therefore, if calculation is done as per option 1, then solar-
powered lighting load will be 4.58 kW. If calculation is done as per option 2, then solar-powered
lighting load will be 9.05 kW.
Note In case installation of a solar photovoltaic system has been planned on site to meet the requirements of GRIHA Criterion 18, the
electricity generated from this PV plant can also be used to power exterior lights. However, the solar energy requirements of Criterion 6
are independent of the requirements of Criterion 18.
Guide to use GRIHA online evaluation tool
Depending on the points that are being attempted in a project, click on the relevant boxes in the
‘Goals’ section. Given below is a snapshot of the GRIHA Criterion 6 template for a project where
all 3 points are being attempted. As soon as the user clicks on the box, the related compliance
documents get ticked automatically bringing to the notice of the user to provide all the required
documentation. Required supporting drawings and word documents can be uploaded using the
template.